Phase 2 Improvement works A713 Ayr to Dalmellington Road

The Ayrshire Roads Alliance, as part of its ongoing programme to improve the condition of the road network, will be carrying out essential road resurfacing works on two sections of the A713 Ayr to Dalmellington road.


Phase two - A713 immediately North of Polnessan


This phase is due to start on Monday 12 July and will continue for up to two weeks.


All preparatory work will be undertaken during weekdays between 08.00 until 17.00 and convoy traffic management will be in place, with delays possible.


To lay the new surface course, it is anticipated that four overnight road closures will be required on Monday 19, Tuesday 20, Wednesday 21 and Thursday 22 July from 20.00 until 06.00, when signed accordingly.


An alternative route will be signed via B741 to New Cumnock, A76 to A70 Dettingen Roundabout Cumnock, to A70 Coylton, to B742 to re-join the A713 and vice versa.


There will be no access to or from the adjoining B730 Drongan Road during the overnight closures.


Electronic Variable Message Signs will be placed on the A713 to inform the travelling public of each overnight closure.


Emergency Access will be maintained at all times throughout the duration of the works.


It is hoped that the resurfacing work will be completed within the timescales stipulated, however the work is weather dependent and any unforeseen difficulties could result in a delay. Any updates to the work will be published on the Ayrshire Roads Alliance website www.ayrshireroadsalliance.org